Readiness Assessment 5/6


Readiness Assessment 5/6 is now closed.

The overall purpose of Programme Readiness Assessments is to provide an accurate view of participant readiness, allowing data-driven decisions to be made, particularly in relation to upcoming Milestones and Control Points.  

Readiness Assessment 5/6 is a critical input and evidence capturing mechanism to inform and support wider M10 readiness tracking activity and will enable the Programme to identify any risks and issues in advance of Go-Live. 

Readiness Assessment 5/6 focuses on: 

  • Milestones M10 (Central systems ready for migrating Meter Point Administration Numbers (MPANs))
  • M11 (initiation of the migration of MPANs), as well as the pre-requisites for M10, e.g. Qualification readiness.  
  • Input into Control Points 3 and 4 (readiness for start of Migration) 

Thank you to all participants who responded to Readiness Assessment Three (5/6). This survey is now closed. 

Q&A.jpg

christina-wocintechchat-com-RMweULmCYxM-unsplash.jpg

RA 5/6 launched on Monday 28 April 2025 and was emailed to all Principal Contacts for completion. Participants had three weeks to complete the survey. 

All Programme participants were expected to respond to Readiness Assessment 5/6 (RA5-6) in line with their Balancing and Settlement Code (BSC) obligations. 

If you didn't complete the survey, please email the Programme Party Coordination (PPC) team at [email protected]  as soon as possible. 

The PPC team will review and analyse the survey responses. RA 5/6 will inform the development of two key deliverables:

  1.  RA 5/6 Overall Report
  2. Participant Individual Reports. 

Requirement to complete Readiness Assessment 5/6

Under Clause 12.12.1 of the Balancing and Settlement Code (BSC) obligation, each MHHS participant is obliged to: 

Provide the Authority, the MHHS Independent Assurance Provider or MHHS Implementation Manager with such information as they may reasonably request in relation to MHHS Implementation, including regarding the MHHS participant’s planning for and progress in relation to MHHS Implementation (including progress against its own Programme plan).”

This means that all MHHS participants had an obligation to respond to Readiness Assessment 5/6.

Please note that the Programme Steering Group (PSG) and Ofgem will be notified of which participants have and have not responded to Readiness Assessment 5/6

If you have any questions about Readiness Assessment 5/6, please contact your PPC representative or the wider PPC team at [email protected] 

blue clock