Milestone 16 (M16): Cutover to the new Settlement Timetable
Milestone 16 (M16): Cutover to the new Settlement Timetable, is the point at which we move from the legacy 14-month settlement timetable to the new shortened settlement timetable.
The transition to the new Settlement Timetable will be implemented in stages:

The Settlement Timetable Expert Group (STEG) was established by the Migration & Cutover Advisory Group (MCAG) and tasked with developing the success criteria and monitoring migration and settlement performance to enable the required decisions to be taken to shorten the Settlement Timetable. For more information about STEG activities and the STEG delivery plan please visit the STEG page of this website.
Recommendation to reduce the Settlement Timetable
The recommendation to reduce the Settlement Timetable was directed by Ofgem as part of the introduction of MHHS.
The below table provides a timeline for the development of the proposal:

Further information can be found in the relevant papers in the Quick Links.
Target Operating Model for MHHS DWG's recommendation to Ofgem
Future enabling the market-wide settlement reform TOM - September 2019
Electricity Retail MHHS: Decision - April 2021
Ofgem Final MHHS decision and Business Case - April 2021
MHHS Transition Design
The process and timings for the transition to the new Settlement Timetable are set out in the Requirements for the Transition to the new MHHS Settlement Timetable with a worked example of the revised Settlement Timetable provided.
Requirements for the Transition to the new MHHS Settlement Timetable
Illustration MHHS Proposal for revised Settlement Timetable cutover [based on 2 July 2027 cutover]
Readiness for M16 and the cutover to the new Settlement Timetable
In July 2026, the Programme issued Readiness Assessment 8 (RA8) which sought to understand participants awareness of the baselined Transition Design and any consequential changes required as a result, and to identify any risks and issues participants may have in becoming ready for M16 and the shortening of the Settlement Timetable. For more information about RA8, please visit the RA8 page of this website.
We are also aware that there are likely to be consequential changes for Central Volume Allocation (CVA) parties as a result of the shortening of the Settlement Timetable. We have a produced an overview of M16 specifically for CVA parties which can be found below:
M16 Overview Information for CVA Parties
CVA parties are out of scope of the MHHS Target Operating Model and are managed directly by Elexon, who have launched an issue group- Issue 122- to look at M16 Readiness for the CVA arrangements. For more information, please visit the Issue 122 page of the Elexon website.
If you have any questions, please email [email protected]