SIT Overarching Exit Reports


When the Systems Integration Testing phase of the MHHS Programme closed, the Programme prepared Exit Reports for each test phase.

The Exit Reports served as a formal checkpoint to ensure that all participants were aligned on achievements, outstanding issues, and the readiness to confidently move into the next phase of the MHHS journey.


fast_track.jpg

SIT Functional & Migration Overarching Exit Report

On Monday 11 August 2025, the MHHS Programme issued the SIT Functional & Migration Systems integrator (SI) Overarching Exit Report for industry review, and is available to view below. 

The Cycle 3 version of this report was reviewed by industry, and this final version was an update to include the outcomes from SIT-A Settlement and Regression testing. 

Thank you to all participants who submitted comments as part of this review. The review period is closed.  

The purpose of this industry review was to provide participants insight into the report. This was a key document, recommended by the Systems Integration Testing Working Group (SITWG), and was approved by the Extraordinary Systems Integration Testing Advisory Group (eSITAG) on Friday 15 August 2025, to pass a Tier 2 Milestone. This marked closure of the Functional & Migration Testing stage of the MHHS Programme.

You can view the SIT Functional & Migration SI Overarching Exit Report and SIT Functional & Migration SI Overarching Test & Defect Extract below, which contained the test, requirement and defects status for SIT participants. 

SIT Functional & Migration Overarching Exit Report

SIT Functional & Migration SI Overarching Test & Defect Extract


SIT Operational Overarching Exit Report

On Tuesday 5 August 2025, the MHHS Programme issued the SIT Operational Systems integrator (SI) Overarching Exit Report for industry review, and is available to view below. 

Thank you to all participants who submitted comments as part of this review. The review period is closed.  

The purpose of this industry review was to provide participants insight into the report. This was a key document, recommended by the Systems Integration Testing Working Group (SITWG), and was approved by the Extraordinary Systems Integration Testing Advisory Group (eSITAG) on Friday 15 August 2025, to pass a Tier 2 Milestone. This marked closure of the Operational Testing stage of the MHHS Programme.

You can view the SIT Operational SI Overarching Exit Report and SIT Operational SI Overarching Test & Defect Extract below, which contained the test, requirement and defects status for SIT participants. 

SIT Operational Overarching Exit Report

SIT Operational SI Overarching Test & Defect Extract

exit.jpg

exit_2.jpg

SIT Non-Functional Overarching Exit Report

On Friday 18 July 2025, the MHHS Programme issued the SIT Non-Functional Systems integrator (SI) Overarching Exit Report for industry review, and is available to view below. 

Thank you to all participants who submitted comments as part of this review. The review period is closed.  

The purpose of this industry review was to provide participants insight into the report. This was a key document, recommended by the Systems Integration Testing Working Group (SITWG), and was approved by the Systems Integration Testing Advisory Group (SITAG) on Wednesday 6 August 2025, to pass a Tier 1 Milestone. This marked closure of the Non-Functional Testing stage of the MHHS Programme.

You can view the SIT Non-Functional SI Overarching Exit Report and SIT Non-Functional SI Overarching Test & Defect Extract below, which contained the test, requirement and defects status for SIT participants. 

SIT Non-Functional Overarching Exit Report

SIT Non-Functional SI Overarching Test & Defect Extract