The objective of the SIT Non-Functional Overarching Test Readiness Report for Theme 1 was to demonstrate the preparedness of testing efforts for each organisation that entered SIT Non-Functional Testing (Theme 1).
As a key milestone before testing activities started, the report aimed to ensure that all necessary components and prerequisites were in place to conduct testing efficiently and effectively.
This report was approved at the Extraordinary Systems Integration Testing Advisory Group (eSITAG) meeting on Friday 28 February 2025.
You can view the approved document below:
SIT Non-Functional Overarching Test Readiness Report (Theme 1)
SIT Non-Functional Overarching Test Readiness Report (Themes 2 & 3)
A previous version of this report (v0.3) was approved with caveats at the Extraordinary Systems Integration Testing Advisory Group (eSITAG) meeting on Friday 28 March 2025.
The caveats surrounded the fact that some participants hadn't fully completed all Pre-Integration Testing (PIT) activities to formally certify SIT readiness, but it was determined that these items could be covered via work-off plans and SIT could proceed as planned.
The objective of the SIT Non-Functional Overarching Test Readiness Report for Theme 2 and 3 was to demonstrate the preparedness of testing efforts for each organisation that entered SIT Non-Functional Testing (Theme 2 and 3). As a key milestone before testing activities started, the report aimed to ensure that all necessary components and prerequisites were in place to conduct testing efficiently and effectively.
This updated version, available below, reflected the completed final state since all outstanding PIT activities and work-off plans were completed.
SIT Non-Functional Overarching Test Readiness Report (Themes 2 & 3)